Drafting RERA Agreements for Builders in India: Key Clauses
Drafting a RERA agreement for real estate builders means turning the Real Estate (Regulation and Development) Act, 2016 and its state rules into a signed contract that matches the statutory model format, discloses project details accurately, and fixes possession, defect-liability and refund terms exactly as the law requires. Builders who copy an old sale-deed template without this exercise often find clauses struck down or unenforceable before the state RERA authority.
Key Takeaways
- Model format is mandatory: Once a project is registered under Section 3, the agreement for sale must broadly follow the annexure format prescribed under the relevant state's RERA rules, not a builder's own template.
- Carpet area governs pricing: Section 2(k) defines carpet area precisely, and consideration must be stated against that figure, not "super built-up area" as was common practice before 2016.
- Delay carries statutory interest: Under Section 18, a builder who misses the disclosed possession date owes interest at the State Bank of India's highest marginal cost of lending rate plus 2%, or must offer a refund.
- Defect liability runs five years: Section 14(3) fixes a five-year structural defect liability period after handover, regardless of what a builder's own warranty clause says.
- Seventy percent of funds are ring-fenced: Section 4(2)(l)(D) requires builders to deposit 70% of amounts collected from allottees into a separate escrow account, withdrawn only against certified construction progress.
At a Glance: RERA Agreement Essentials
| Requirement | Statutory Basis | Practical Effect on Drafting |
|---|---|---|
| Model agreement format | State RERA Rules, Annexure A (varies by state) | Builders must use the prescribed format as the base, adapting only permitted variable fields |
| Carpet area disclosure | Section 2(k) | Agreement must state carpet area, not super built-up or saleable area, for pricing |
| Possession timeline | Section 11(4)(a), Section 18 | Disclosed date must match the registered project timeline; delay triggers interest or refund |
| Structural defect liability | Section 14(3) | Five-year rectification obligation survives handover irrespective of contrary clauses |
| Escrow account | Section 4(2)(l)(D) | 70% of collections held separately; withdrawal needs engineer, architect and CA certification |
| Common area handover | Section 11(4), Section 17 | Agreement must specify handover date to the association of allottees |
| Dispute forum | Sections 31, 43, 44 | Complaints lie before the state RERA authority and appellate tribunal |

What Is a RERA Agreement for Sale and Why Does It Differ From a Regular Sale Agreement?
A RERA agreement for sale is the statutory contract format that a registered project must use once a builder begins accepting money from allottees, and it differs from an ordinary sale agreement because its core terms are prescribed by rule rather than left to negotiation. The builder can add project-specific schedules, but cannot dilute the statutory protections.
Before 2016, builders in India largely used their own templates. Clauses on possession dates, penalty for delay, and area calculation varied widely, and allottees had little standard protection if a project stalled.
The Act changed that by tying the agreement for sale directly to the information a builder discloses at the time of project registration under Section 4. Rajasthan's own RERA Rules, 2017, for instance, prescribe a model format in an annexure that Jaipur-based builders and developers active across the state must adapt rather than draft from scratch.
1. Confirm the Statutory Disclosures Before Drafting
Before a single clause is drafted, the builder's registration file under Section 4 needs to be checked against what will appear in the agreement. The project registration number, sanctioned building plans, layout plan, and the title report on the land must all match what was filed with the authority.
Any mismatch between the registered disclosures and the agreement's recitals becomes a documentation defect that an allottee, or the authority itself, can flag later. Builders working across Rajasthan and neighbouring states also need to confirm which state's model format applies, since the annexures are not identical.
This is one reason builders without an in-house legal team often engage a one-time contract review specifically at this stage, before the agreement goes to print for multiple bookings.
2. Define Carpet Area and Consideration Precisely
Carpet area must be defined and calculated exactly as Section 2(k) sets out: the net usable floor area within the walls, excluding balconies, terraces and common areas unless specifically included by rule. The consideration figure in the agreement must be tied to that carpet area, not a super built-up figure.

This single change eliminated a long-standing source of disputes. Builders who priced flats on loading factors of 30% or more found allottees paying for common space they never separately understood as chargeable.
The agreement should itemise the base price against carpet area, then list other charges (parking, club membership, maintenance deposit, GST) as separate line items rather than folding them into a single lump sum. A payment schedule tied to construction milestones, rather than a flat calendar schedule, keeps the agreement consistent with how RERA expects escrow withdrawals to work.
3. Draft the Possession Timeline and Delay Compensation Clause
The possession clause must state the exact date disclosed at registration and must not be qualified by vague conditions that effectively remove the builder's obligation. Section 18 fixes the consequence of a missed date: interest at the State Bank of India's highest marginal cost of lending rate plus 2%, payable monthly, or a full refund with interest if the allottee chooses to withdraw.
Force majeure clauses are where many builder-drafted agreements go wrong. A clause that lists "any event beyond the builder's reasonable control" without naming specific events (war, flood, government-ordered lockdown, or similar) is unlikely to survive scrutiny before the authority, because it effectively rewrites the statutory delay remedy.
A narrow, named list of force majeure events, cross-referenced to the actual causes recognised in the project's registration extension applications if any were filed, keeps the clause both usable and compliant.
4. Build in the Structural Defect Liability and Common Area Clauses
Section 14(3) requires a builder to rectify structural defects, or defects in workmanship, quality or provision of services, for five years from the date of handing over possession, without charge to the allottee. This obligation cannot be shortened by contract; it can only be supplemented with more generous terms.
The agreement should set out a clear notice mechanism: how an allottee reports a defect, the timeframe for the builder to inspect, and the timeframe for rectification. Vague language like "within a reasonable time" invites disputes that a specific number of days would avoid.
Common area handover terms sit alongside this. Section 11(4) and Section 17 require the builder to hand over common areas and facilities to the association of allottees, along with relevant documents, and the agreement should name a target date for that transition rather than leaving it open-ended.
5. Address the 70% Escrow Account and Withdrawal Conditions
Under Section 4(2)(l)(D), a builder must deposit 70% of the amounts realised from allottees for a project into a separate bank account, to be used only for construction cost and land cost of that project. Withdrawals from this account require certification by an engineer, an architect and a chartered accountant confirming the proportion of construction completed.

Although the escrow mechanism itself operates through the builder's banking arrangements rather than the agreement for sale, the agreement should reference the account and reassure the allottee that payments collected are subject to this restriction. Builders sometimes omit this reference, which is a missed opportunity to demonstrate compliance in the contract itself.
This clause matters as much to lenders financing the project as it does to individual allottees, since project finance approvals increasingly check for escrow compliance as a condition of disbursement.
6. Cover Termination, Refund and Dispute Resolution
Cancellation and refund clauses in a RERA agreement cannot override the statutory refund entitlement under Section 18, even where the builder's own template includes forfeiture percentages that exceed what the authority typically treats as reasonable. Tribunals across states have reduced forfeiture clauses that they viewed as one-sided.
The dispute resolution clause should point to the state RERA authority and the Real Estate Appellate Tribunal as the primary forums, consistent with Sections 31, 43 and 44 of the Act. An arbitration clause can sit alongside this for matters outside RERA's jurisdiction, but it should not attempt to oust the authority's jurisdiction over matters the Act specifically assigns to it.
Is a Model RERA Agreement Format the Same in Every State?
No. Each state notifies its own RERA rules under the Act, and the annexure containing the model agreement for sale differs in formatting and some optional clauses from state to state, though the core statutory protections remain constant nationwide.
Rajasthan's RERA Rules, 2017 prescribe their own model format, while Maharashtra, Karnataka, and other states have adopted their own annexures with local variations, such as differing stamp duty references or additional local disclosures. A builder registering projects in more than one state cannot use a single template across all of them without checking each state's specific rules.
This is where pan-India coordination through associated local counsel becomes relevant for developers with projects outside their home state, so that the base agreement is adapted correctly for each jurisdiction rather than assumed to be uniform. (Note: builders should confirm the exact slug reference for this comparison independently.)
Common Drafting Gaps That Draw Regulatory Scrutiny

- Vague force majeure clauses: Broad, undefined language that effectively cancels the Section 18 delay remedy.
- Area confusion: Referring to super built-up or saleable area instead of carpet area as defined in Section 2(k).
- Missing escrow language: No reference to the 70% account, leaving allottees without visibility into fund handling.
- One-sided cancellation terms: Forfeiture percentages that ignore the statutory refund-with-interest entitlement.
- Silent common area timelines: No fixed date for handover to the association of allottees, leaving Section 17 obligations open-ended.
These gaps rarely surface at the point of signing. They surface later, when a delay or dispute forces both sides to read the agreement closely, by which point renegotiation is harder than getting the draft right the first time.
Frequently Asked Questions
Is a RERA agreement mandatory for all real estate projects in India?
It is mandatory for projects that meet the registration threshold under Section 3, generally plot areas above 500 square metres or more than eight apartments. Smaller projects outside this threshold may fall outside mandatory registration, but state rules and local practice should still be checked.
Can builders modify the model agreement format prescribed by state rules?
Builders can add project-specific schedules and annexures, such as fit-out specifications or parking allocation details, but the core statutory clauses on disclosures, possession, defect liability and refund cannot be diluted or removed.
What happens if a clause in the agreement conflicts with a RERA provision?
Section 89 of the Act gives RERA overriding effect over anything inconsistent in any other law or instrument, including a builder-drafted agreement. A conflicting clause is generally treated as void to the extent of the inconsistency, and the statutory provision applies instead.
Does drafting RERA agreements fit better with a retainer or a one-time review?
This depends on how often a builder launches new projects or phases requiring fresh agreements. A developer with one active project may need only standalone drafting and vetting support, while a builder running multiple ongoing launches may find a structured arrangement, discussed in Drafting a General Counsel Retainer Agreement in India, better suited to recurring documentation needs. A comparison of the two models is set out in Retainer Lawyer vs One-Time Contract Review in India.
Builders evaluating their RERA documentation would do well to treat the agreement for sale as a compliance instrument first and a sales tool second: the Real Estate (Regulation and Development) Act, 2016, available on the Ministry of Housing and Urban Affairs' RERA portal, and each state's own rules remain the primary reference points, alongside guidance published by the Rajasthan Real Estate Regulatory Authority for projects based in the state.
This content is published for general information only. It is not legal advice, an advertisement, or a solicitation of work, and reading it does not create an advocate-client relationship. In keeping with the Bar Council of India Rules, Riva Legal Associates does not solicit work or advertise.